AST DCCEEW Carbon Credits Data

Updated on: May 26, 2025

Latest Event


  • May 2025 Additional Comments on Implementation
  • On May 21, 2025, AST Clean issued additional comments regarding implementation, stating it has begun publishing more information on the ACCU scheme project register.
  • AST Clean highlighted that this is a welcome change that improves transparency and shows how the ACCU scheme works to accelerate carbon abatement for Australia.
  • The additional data published on May 21, 2025 includes crediting period start and end dates for all projects, permanence period start dates for all sequestration projects; will continue to issue remaining project data in stages over next 2 months (up to Jul. 21).

On Sep. 16, AST DCCEEW proposed rules re carbon data transparency.

  • AST DCCEEW issued exposure draft of the Carbon credit (carbon farming initiative) amendment (2024 measures no. 2) rules 2024, to make amendments to the Carbon credits (carbon farming initiative) rule 2015, and issued draft explanatory statement.
  • Aimed at improving transparency of the Australian carbon credit unit (ACCU) scheme.
  • Follows AST DCCEEW Aug. 2023 sought feedback on proposals re a scheme, #183009.
  • Background
  • In 2022, AST GVT appointed an independent panel to review the integrity of ACCUs under Australia’s carbon crediting framework; the review recommended several changes to clarify governance, improve transparency, enhance confidence re integrity.
  • It recommended amending provisions in the legislation to maximize transparency, data access, data sharing, while enabling protection of privacy, commercial-in-confidence information, for greater public trust in scheme arrangements (recommendation 4).
  • On Aug. 25, 2023, the. AST DCCEEW released a discussion paper, outlining options for implementing several of the review’s recommendations, as discussed in #183009.
  • The amendment rule is informed by feedback received during this public consultation.
  • Proposal
  • AST Clean shall publish additional ACCU scheme project data and information on the AST Clean's website, including improved description or alternatively detail of project activities for all projects under all methods, type of estimation approach used.
  • Plus, description of any suppression mechanisms identified, removals of suppressors re the project, project crediting period start, end dates, project permanence start date.
  • Start date for the chosen tool or modelling approach used to calculate abatement for each carbon estimation area (CEA) of a project, published link in the project register to any enforceable undertakings, names of all agents involved in project’s management.
  • Specifies two exemptions to publishing the information above, including withholding the information is required to protect or respect Aboriginal tradition, or publication may threaten, damage or cause harm to a threatened ecological community/species.
  • Consultation End
  • AST DCCEEW to host an information session on Sep. 26, 2024; registration is required.
  • The consultation closes on Oct. 7, 2024.
  • Dec. 2024 Credit Scheme Amendments
  • On Dec. 20, 2024, AST DCCEEW amended Carbon credits (carbon farming initiative) rule 2015 to build public trust in the ACCU Scheme by improving transparency.
  • The amendment brings the Carbon credits (carbon farming initiative) amendment (2024 measures no. 2) rules 2024 into effect.
  • AST Clean has a transition period of 6 months to implement publication requirements.
  • Feb. 2025 Implementation
  • On Feb. 3, 2025, AST Clean published transparency changes for the ACCU scheme.
  • AST Clean will transition the project register to publish the new information in the next six months' time; these updates will be completed by Jun. 20, 2025.
  • It will work with participants to confirm the data to be published on project register.
  • May 2025 Additional Comments on Implementation
  • On May 21, 2025, AST Clean issued additional comments regarding implementation, stating it has begun publishing more information on the ACCU scheme project register.
  • AST Clean highlighted that this is a welcome change that improves transparency and shows how the ACCU scheme works to accelerate carbon abatement for Australia.
  • The additional data published on May 21, 2025 includes crediting period start and end dates for all projects, permanence period start dates for all sequestration projects; will continue to issue remaining project data in stages over next 2 months (up to Jul. 21).
Regulators
AST Clean; AST DCCEEW
Entity Types
Corp
Reference
PR 5/21/2025; PR 2/3/2025; PR, RF F2024L01726, 12/20/2024; CP, PR, 9/16/2024; ESG; Citation: Carbon credits (carbon farming initiative) rule 2015; Carbon credits (carbon farming initiative) amendment (2024 measures no. 2) rules 2024;
Functions
Compliance; Environment; Financial; Legal; Operations; Reporting
Countries
Australia
Category
State
N/A
Products
Commodities; Corporate
Rule Type
Final
Regions
AP
Rule Date
Sep 16, 2024
Effective Date
Jul 21, 2025
Rule ID
226388
Linked to
Reg. Last Update
May 21, 2025
Report Section
International