ASX First Industry Wide Test Planned

Updated on: Apr 22, 2025

Latest Event


  • Apr. 16, 2025 ASX Update
  • On Apr. 16, 2025, ASX issued update announcing delay to service release 15 implementation following first industry-wide test that took place on Apr. 12, 2025.
  • In addition, updated IWT1, IWT2 notices linking to latest IWT3, go live information.
  • Non-functional defect identified during IWT1 system start-up, requiring manual start-up of some system components; however, it was noted that the defect did not impact performance or functional elements of service release 15 (SR15) during the test.
  • ASX working with vendor to identify root cause and develop fix, which will undergo extensive internal validation testing and governance procedures; second IWT combined with BCP proceeding May 3, 2025 using SR15 to validate corrective release.
  • Delay to previously scheduled IWT3 and go-live date to ensure safe and stable rollout.
  • Revised go-live date will be provided with minimum 3 weeks' notice following IWT2.

On Feb. 25, ASX planned first industry wide test for service release 15.

  • ASX will conduct first of three industry wide test (IWT) events for Service release 15 (SR15); all trading participants are expected to participate in this test.
  • Published release gave details on registration; declaration; test availability, conditions.
  • Industry Wide Test Events
  • During each IWT event, ASX will run all session states on a compressed schedule.
  • Testing include new session states, new trade report codes, FIX drop copy service; simulation of opening single price auction for selected securities, late closing auctions.
  • All trading participants are being requested to take part in the events, while vendors and approved market operators (AMOs) are being strongly encouraged to join too.
  • Trading participants must attest they can connect and process new functionalities.
  • Test environment will restore good to cancel/good to date orders, cancel undisclosed, iceberg orders; limited to ASX trade connections only, with no CHESS/signal B access.
  • The system will rollback following testing, ensuring a normal open on Apr. 14, 2025; participants should remove Apr. 12 transactions from their applications after the test.
  • Post-test, participants must confirm test status to customer technical support (CTS) by 1pm AEST on Apr. 12, 2025, submit the attestation form by 2pm on May 10, 2025.
  • Effectiveness
  • Registrations regarding IWT1 must be submitted to ASX CTS by Apr. 4, 2025.
  • The three scheduled IWT dates are as follows: Apr. 12, 2025 (IWT1), May 3, 2025 (IWT2 - ASX BCP weekend), and May 10, 2025 (IWT3 - go-live readiness).
  • Mar. 2025 Second Industry Test
  • On Mar. 31, 2025, ASX said the second IWT will take place on May 3, which will be combined with the first of two business continuity testing (BCP) events in 2025.
  • ASX said that it will conduct three industry tests in the production environment.
  • IWT1 on Apr. 12, IWT2 May 3 (BCP Weekend), and IWT3 May 10 (Go live readiness).
  • The market will run through all session states to allow customers to test functional changes including new session states, new trade report codes and FIX drop copy.
  • ASX requests all participants take part; vendors, AMOs are also encouraged to do so.
  • Participants must attest they can successfully connect and process new functionality.
  • Apr. 1, 2025 Cboe AST BCP Event
  • On Apr. 1, 2025, Cboe AST said it will provide unattended client testing in the Cboe titanium production environment on Apr. 12, 2025 and May 10, 2025 to assist clients perform testing related to ASX SR15 IWTs, and provided related timetable.
  • A BCP event will be held to failover from primary to standby instances in the Equinix SY5 data center on May 3, 2025; trades performed during test will not flow to CHESS.
  • In Apr. 2025, ASX issued notice of revisions re ASX service release 15, see #250393.
  • Apr. 10, 2025 ASX Notices
  • On Apr. 10, 2025, ASX updated notice 0184.25.02 re the first IWT for service release 15 on Apr. 12, 2025, and notice 0326.25.03 re the second IWT/BCP on May 3, 2025.
  • Testing period for IWT 1 will be 08:30 to 12:30 AEST; test information is specified.
  • The testing period for IWT 2/BCP will be from 08:30 to 14:00 AEST; registrations for IWT 2/BCP should be returned by close of business by Apr. 25, 2025.
  • Times may also be subject to change based on participant feedback from IWT 1.
  • Apr. 16, 2025 ASX Update
  • On Apr. 16, 2025, ASX issued update announcing delay to service release 15 implementation following first industry-wide test that took place on Apr. 12, 2025.
  • In addition, updated IWT1, IWT2 notices linking to latest IWT3, go live information.
  • Non-functional defect identified during IWT1 system start-up, requiring manual start-up of some system components; however, it was noted that the defect did not impact performance or functional elements of service release 15 (SR15) during the test.
  • ASX working with vendor to identify root cause and develop fix, which will undergo extensive internal validation testing and governance procedures; second IWT combined with BCP proceeding May 3, 2025 using SR15 to validate corrective release.
  • Delay to previously scheduled IWT3 and go-live date to ensure safe and stable rollout.
  • Revised go-live date will be provided with minimum 3 weeks' notice following IWT2.
Regulators
ASX; Cboe AST
Entity Types
B/D; Corp; Exch; Inv Co
Reference
Nt 0372.25.04, 0184.25.02, 0326.25.03, 4/16/2025; Nt 0184.25.02, 0326.25.03, 4/10/2025; Nt 0008/25, 4/1/2025; Nt 0326.25.03, 3/31/2025; Nt 0184.25.02, Form, 2/25/2025
Functions
BCS; Compliance; Financial; Operations; Reporting; Technology; Trade Reporting; Trading
Countries
Australia
Category
State
N/A
Products
Corporate; Derivatives; Equity; Fund Mgt; Securities
Rule Type
Final
Regions
AP
Rule Date
Feb 25, 2025
Effective Date
May 3, 2025
Rule ID
244943
Linked to
Reg. Last Update
Apr 16, 2025
Report Section
International